Stand design and production

How a stand comes into being, from the brief to the workshop check: which facts the drawing cannot start without, how the concept is approved, what the technical drawing contains, when system, modular or custom timber is chosen, and why production ends weeks before the fair.

01

The brief: no drawing without six facts

02

Concept, technical drawing and approvals

03

Which stand type when

Stand types compared by fit, limits and build time
TypeWhen it fitsIts limitBuild-up
System stand (maxima profile)Short build window, plots of 24 m² and under (Tüyap rule), first fair, dense fair programmeNo free form; brand differentiation comes from graphics and facade claddingOne day
Modular standMid-sized plots, panel and lightbox layouts, product showcasesHeight and decks limited; extra structure for heavy productsOne to two days
Custom timber buildCorner and island plots, above 25 m², painted surfaces and free form, brand experiencePaint and cutting banned in the hall: every part is finished in the workshop; longest production timeTwo to three days
Double deckerLarge plots, closed meeting needs, visibilitySteel structure, engineer approval, upper deck at most half the plot (Tüyap)Three to four days

If your fair date is set, the countdown has started

The stand calendar starts the day the plot contract is signed. Send the fair name, date and plot size; within two business days we come back with a concept visual and an itemised quote. Asking for a quote commits you to nothing.

Request a quoteTalk to us first

04

Production: work finished in the workshop causes no trouble in the hall

24 m²
Tüyap plots at or under this size: modular systems only, no second deck (1 March 2026)

Source: Tüyap stand technical rules (MAKTEK 2026)

40%
mandatory open share of every aisle-facing side (Tüyap)

Source: Tüyap stand technical rules

05

Frequently asked questions

How much time should we allow for design?
Is the 3D visual charged?
Who prepares the graphic files?
Can a small touch-up be painted in the hall?

We read the technical manual so you do not have to

We submit the stand project to the organiser together with the engineer's approval, the electrical load declaration and the fire certificates. The crew entering the hall on build day is registered, certified and has worked in that venue before.